Modernisation during technological downtime is always a struggle with time.
48 hours, difficult housing conditions, strict health and safety regulations.
DESCRIPTION OF THE SCOPE OF PERFORMED MODERNIZING WORK
Preparing design documentation of modernization in the mechanical and electrical sectors.
Dewatering the ice water system with the disposal of glycol volume.
Dismantling thermal insulation and the set of suction and discharge collectors.
Dismantling the currently operating pumping systems BELL&GOSSET.
Execution of prefabrication of suction and discharge collectors DN300 PN10/16.
Assembly of suction and discharge collectors DN300 PN10/16 with necessary supports.
Assembly of 3pcs of centrifugal monoblock pumps and adjustment of steel mounting frame.
Assembly of fittings: shock absorbing connectors ZKB, check valves 801, shut-off dumpers.
Assembly of counterbalance valves Oventrop Hydrocontrol VFC DN2.
Assembly of a set of manifolds.
Anti-corrosion protection of installation elements.
![]()
![]()
![]()
![]()